CSL to Build New Transhipment Vessel for BCI Minerals
As part of CSL’s comprehensive transhipment solution, the custom-designed transhipper will handle 5.35 million metric tons of salt and 140,000 metric tons of sulfate of potash per year. Loading will take place at BCI’s jetty loadout facility in Cape Preston, Western Australia, with the vessel navigating 12-15 nautical miles to transfer the cargo to ocean-going ships from Handysize to Newcastle Max.
New Vessel Highlights
- Shallow draft to maximize cargo lift within tide and channel constraints
- Total deadweight of approximately 16,000 metric tons
- Gravity discharge, suitable for loading salt, sulfate of potash and other dry bulk commodities onto ocean-going vessels with a deadweight of up to 207,000 metric tons
- High maneuverability, with double-ended propulsion
- Four azimuth drives and an integrated diesel-electric propulsion and powering system
- Single-point loading system with a loading rate of 3,300 metric tons per hour
- Self-unloading system with a discharge rate of 4,000 metric tons per hour
Construction of the new vessel will begin in spring 2026 with delivery scheduled in mid-2027. In the interim, beginning in the second half of 2026, CSL will provide a vessel on time charter to deliver transhipment services to the Mardie Project while the new dedicated vessel is under construction.
Horizons: Navigating Tariffs and Trade Winds
The Great Lakes-St. Lawrence Seaway system, a vital artery for North American commerce, faces turbulent waters amid escalating trade tensions. As 2026 progresses, tariffs imposed by the U.S. administration under... Read More
AGLPA Launches Study to Assess Increasing Trade Between the Great Lakes and Inland Waterways
A study is underway to assess the economic opportunities and transportation benefits of increasing maritime cargo shipments between the Great Lakes and U.S. inland waterways. The American Great Lakes Ports Association (AGLPA), Ports... Read More